1. Preliminary preparation
Firstly, notify the user to tidy up the cabinet without affecting their normal work.
Then, based on various factors such as the topology of the network, the existing equipment situation, the number of users, and user grouping, draw the wiring diagram and equipment location diagram inside the cabinet.
Next, prepare the necessary materials: network jumpers, label paper, and various types of plastic zip ties (strangle the dog).
2. Organize the cabinet
Install network cabinet:
You need to do the following three things by yourself: first, use the screws and nuts of the random frame to tighten the fixing bracket; Secondly, topple the network cabinet and install the movable wheels; Thirdly, adjust and add baffles on the fixed frame according to the position of the equipment.
Organize the route:
Group the network cables, usually less than or equal to the number of cable racks behind the cabinet. Tie the power cords of all devices together, insert the plug into the through hole at the back, and search for each device through a separate cable rack.
Fixed equipment:
Adjust the baffle in the network cabinet to the appropriate position, so that the administrator can see the operation of all devices without turning on the cabinet door, and add baffles appropriately according to the number and size of devices. Be sure to leave a certain gap between the baffles. Place all the switching and routing devices used in the cabinet according to the pre drawn diagram.
Network cable labeling:
After all the network cables are connected, they need to be labeled. Wrap the prepared instant stickers around the cables and mark them with a pen (usually indicating the room number or purpose). The labeling should be simple and easy to understand. Cross network cables can be distinguished from regular cables by using instant stickers of different colors. If there are too many devices, they need to be classified and numbered, and labeled.
3. Post production work
Electrical testing:
After confirming the correctness, turn on the power and conduct network connectivity testing to ensure the normal operation of the user - this is the most important.
Document update:
Update the document on the contents of this cabinet organization. Redraw the equipment layout diagram and network cable connection diagram. The equipment number and network cable identification should be indicated on the diagram for maintenance reference. It is best to include the username as an item in the diagram. Finally, indicate the date and contact person.